Define the output your operation can use
The target is recorded delivered portfolio production in kWh per 15 minutes. A low observation can reflect weak sunlight or restricted delivery. Estimating energy available before curtailment would require a separate target and evidence.
The forecast and storage panels connect interval energy with a downstream calculation on the same clock. Energy production uses kWh per interval; battery state of charge uses percent of capacity. Keeping these quantities distinct matters when specifying an interface for another system.
The modeled storage policy uses a 1 MWh battery starting at 20%, takes 25% of forecast energy from 08:00 to 16:00, and discharges at 75 kW from 17:00 to 23:00, with ideal efficiency and 20 to 90% limits. This calculation explains how a forecast can feed a downstream storage interface.
Make the issue cutoff enforceable
Weather has a valid time for the interval it describes and an issuance time for when it became available. A historical replay must retain weather vintages and select only those available at the configured previous day local time cutoff. Later revisions would give the replay information unavailable for the order.
Production observations must come from intervals completed before that cutoff. The interface rejects duplicate records and requires the supplied issue time to match the configured cutoff. It applies saved preprocessing and models without retraining or using delivery day actuals at inference.
The output covers the next local day. Localize each midnight separately before conversion to UTC: daylight saving transitions produce 92 or 100 quarter hours, versus 96 on an ordinary day. A fixed 24 hour array would represent the wrong delivery intervals.
The issue cutoff defines the forecast inputs
Freeze the issue time inputs
Use weather issuances available by the cutoff and production intervals that have already completed.
issue time ≠ valid timeApply the saved forecast pipeline
Saved preprocessing, causal features and the released model produce predictions for supported rows.
same release contractReturn the complete delivery clock
Keep the next local day's 15 minute intervals, with nonnegative kWh and an availability status. Unsupported rows remain unavailable.
kWh / 15 minavailability status
Specify what happens when support is missing
The release freezes the site roster, weather mapping, transformations and model. Supported rows receive nonnegative portfolio forecasts. Missing support leaves an interval present with an unavailable prediction and explanatory status, rather than zero or a partial portfolio total. Adding sites requires a release decision.
Input and model bundle identities, missing weather information and interval availability make the output inspectable. The availability grid explains target completeness, separate from the historical evaluation below: missing labels reduce scoring evidence, while observed zeros remain valid targets. Label availability and forecast availability are different checks.
Release checks found exact matches between saved central forecasts and bounds and packaged inference output. This establishes implementation parity; accuracy requires comparison with observed production. For a new integration, specify measurement arrival, database, scheduling and storage responsibilities around the inference interface.
A missing target is different from zero
Set separate acceptance criteria for accuracy and uncertainty
Saved P25 and P75 models share the central forecast’s inputs and preprocessing. Nonnegative reconstruction anchors their endpoints around the unchanged central estimate, with adjustments counted in diagnostics. The resulting pointwise band is nominally 50% and uncalibrated; ordering its endpoints does not establish coverage.
The bounds describe individual 15 minute outcomes. Summing lower or upper endpoints does not produce daily P25 or P75 totals, because whole day uncertainty depends on relationships between intervals. The forecast plot explains that interval contract; it does not report calibration.
A historical evaluation for March 8 to May 31, 2026 recorded 32.92% WAPE and 46.18% pointwise containment against nominal 50%. It scored 6,037 labeled intervals from 8,156 slots for the frozen 29 site portfolio; 2,119 targets were missing and some labels included partial device sums. The holdout had already been examined, with no independent calibration split. These results describe that observed subset.
For commissioning, agree how the exact delivered output will be evaluated: its target, issue time evidence, unavailable intervals and uncertainty. That gives the team concrete acceptance criteria before connecting a forecast to an operational workflow.